Question No : 1
A project manager is working for an organization in country A and has been tasked with opening the first brick-and-mortar store in country B. The sponsor has identified the city for the store and wants to minimize any potential issues with the local government.
Which action should the project manager take to address the sponsor's request?

Answer:

Question No : 2
A hybrid project manager has taken over a large-scale software development project m a highly regulated environment. During a handover session the outgoing project manager explains that they devised their own status reports which is different from the project management office's (PMO's) status report style. The project stakeholders are extremely particular about the information they receive in updates and do not believe the PMO's status reports have sufficient enough information
How should the new project manager proceed?

Answer:

Question No : 3
A project manager is part of a global project team and is in charge of managing the scope defined by their country. There is a clear division regarding which pieces of the scope should be treated by global and local teams. During the last sprints, the project manager has been receiving requests that the global team should handle.
What should the project manager do in this situation?

Answer:

Question No : 4
A project manager is leading a project that has been in execution for 1 year. An experienced team member is performing well, but often disagrees with the project manager and refuses to implement their decisions. Part of the team supports the team member's defiance, while the other team members do not.
What should the project manager do?

Answer:

Question No : 5
A project manager acquired information from the market that would reduce the business value being delivered by an ongoing protect Based on that information, the project manager believes the project should be stopped
How should the project manager handle the situation?

Answer:

Question No : 6
A team needs to follow defined cybersecurity compliance that is mandatory for a customer project .
What should the project manager do to monitor compliance in the project?

Answer:

Question No : 7
A project manager is in a learn meeting and the project team requires a decision to be made about a new suggested timeline due to an impact from a potential scope change.
What should the project manager do?

Answer:

Question No : 8
The project manager has initiated the project and the team's roles and responsibilities have been assigned. In preparation for the development of the project management plan, the project manager reviews lessons learned from previous projects and discovers that the same team has been missing delivery dates.
What should the project manager do to ensure timely delivery?

Answer:

Question No : 9
A software delivery project began having technical impediments. The issue may cause a delay of the deliverables. The technical service team has been working on the issue, but the issue is unresolved even after 1 week of maintenance.
What should the senior project manager do now?

Answer:

Question No : 10
An agile team has been struggling to keep up with the planned pace, which is frequently resulting in sprint failures.
What should the project manager do to help avoid this situation in the future?

Answer: